Capital Improvement Projects
Capital Improvement Projects
The funding for this project came from a few places. First, we have a Capital Improvement account in which we set aside funds for career and technical education program enhancements. This will be used for the enhancements to our Wilson Talent Center programming.
The second portion of our funding comes from the Headlee Special Education Restoration Millage passed by voters on March 10, 2020. Thank you to our voters for supporting our students!
Much of the funding we receive for special education goes directly to our local districts and the cost of special education outweighs the funding we receive from state and federal agencies. Restoring the millage has allowed us to bring in more dollars to renovate our facilities to meet the needs of our students. We currently have students learning in an external classroom and the classroom has been used beyond its expected life cycle.
Our kids deserve more.
This transformation will take place between June of 2022 and December 2023 if all goes as planned.
This is an extremely exciting time for Ingham ISD as we invest in our student learning space and enhance their educational experience.
Construction/Renovation Timelines for Evergreen, SLC and WTC
The renovation timelines for Evergreen, Secondary Learning Center and the Wilson Talent Center include the following:
Phase I: June 2022 through August 2022, Wilson Talent Center Restrooms will be renovated
Phase 2: July 2022 through March 2023, the Cybersecurity Class at the Wilson Talent Center will be relocated and start a partial remodel.
Phase 3: June 2022 through August 2023
- The North Star School addition will be built combining the Secondary Learning Center and Evergreen into one school.
- The following Wilson Talent Center Programs will be renovated:
- Cybersecurity
- New Media
- School Store
- Programming
- Engineering
- Construction Trades
- New Culinary Space is started
Phase 4: June 2023 through November 2023, the renovation of the current Culinary at the Wilson Talent Center is completed.
By January 2024, all renovation projects for Evergreen, Secondary Learning Center and the Wilson Talent Center will be completed.
Construction/Renovation Timelines for Heartwood School
The renovation timeline for Heartwood School include the following:
Phase 1
March 2023 through May 2023, a more secure entryway and vestibule are added
Phase 2
May 2023 through June 2023, Restrooms 127/128 are renovated
Phase 3
June 2023 through July 2023, Restrooms 204/205 are renovated
Phase 4
May 2023 through September 2023, Restrooms 343/344 are renovated, and cafeteria upgrades are completed.
By October 2023, all renovation projects for Heartwood will be completed.
Construction/Renovation Progress
- Click to see a larger version New Addition Hagadorn Rd 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Heartwood Student Store Renovations 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Heartwood Common Area New Flooring 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Heartwood Main Lobby, Floor Renovations 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Heartwood School Library, renovating flooring and paint 3.28/2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version CyberSecurity and New Media Classroom Space Additions 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version CyberSecurity and New Media Classroom Space Additions 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Culinary Class New Space (Old SLC Gym) 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version Culinary Class New Space (Old SLC Gym) 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version New Culinary Class Plumbing 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version North Star Main Office 3.28.2023 Skip to end of gallery Skip to start of gallery
- Click to see a larger version North Star Gym 3.28.2023 Skip to end of gallery Skip to start of gallery